Control and management of geomechanical state and stability of structural elements of mining engineering elements in open-pit mines based on Big Data collection and analysis
M.V. Rylnikova1, D.A. Klebanov1, V.V. Rybin2, I.Yu. Rozanov2
1 Institute of Comprehensive Exploitation of Mineral Resources of Russian Academy of Sciences, Moscow, Russian Federation
2 Mining Institute Kola Science Centre of the Russian Academy of Sciences, Apatity, Russian Federation
Russian Mining Industry №4 / 2024 p.121-128
Abstract: When developing solid mineral deposits, mining companies face a large number of challenges related to the need of designing and implementing new efficient technological solutions to process information on the state of the mining engineering system. One of the ways to address these challenges is application of the Big Data technologies at all the field development stages. Big Date can ensure sustainable development of mining complexes and efficient management of geotechnological processes at all the mining stages. Among the most important processes in surface mining is the control of geomechanical processes that take place in the rock mass and that are recorded by the monitoring system. The article presents an approach to organising a multilevel integrated system for monitoring the stability of the near-wall rock mass of operating open pits based on Big Data collection and analysis. The proposed approach is based on accounting for (1) the properties and the state of the rock mass, (2) the scale level of the controlled structures. All kinds of data from different types of information sources should be collected in a single information system, where this information will be used for automated calculation of criteria for optimal operation of the mining engineering system. This approach is consistent with the concepts of hierarchical-block structure of the rock mass, within which the open-pit mining operations are performed and the open-pit excavation is created. Implementation of the proposed approach to control the stability of open pit walls requires equipping the mining operations with a wide range of monitoring and control equipment, organization of special geomechanical services, creation of a unified information system to analyze the Big Data, which will make it possible to ensure the required level of safety of surface mining operations.
Keywords: big data, mining engineering system, subsoil development, open pit mining, geomechanical monitoring, data volume management, pit wall stability, safety of mining operations
Acknowledgements: The article was prepatred within the framework of the Russian Science Foundation Grant No.22617600142, https://rscf.ru/project/22617600142/
For citation: Rylnikova M.V., Klebanov D.A., Rybin V.V., Rozanov I.Yu. Control and management of geomechanical state and stability of structural elements of mining engineering elements in open-pit mines based on Big Data collection and analysis. Russian Mining Industry. 2024;(4):121–128. (In Russ.) https://doi.org/10.30686/1609-9192-2024-4-121-128
Article info
Received: 25.05.2024
Revised: 04.07.2024
Accepted: 08.07.2024
Information about the authors
Marina V. Rylnikova – Dr. Sci. (Eng.), Professor, Institute of Comprehensive Exploitation of Mineral Resources of Russian Academy of Sciences, Moscow, Russian Federation; e-mail: This email address is being protected from spambots. You need JavaScript enabled to view it.
Dmitry A. Klebanov – Cand. Sci. (Eng.), Head of Laboratory of Intelligent Systems and Digital Technologies, Institute of Comprehensive Exploitation of Mineral Resources of Russian Academy of Sciences, Moscow, Russian Federation; e-mail: This email address is being protected from spambots. You need JavaScript enabled to view it.
Vadim V. Rybin – Dr. Sci. (Eng.), Associate Professor, Chief of Laboratory of Geomonitoring and Slope Stability, Rock Mechanics Department, Mining Institute Kola Science Centre of the Russian Academy of Sciences, Apatity, Russian Federation Ivan Yu. Rozanov – Cand. Sci. (Eng.), Research Scientist, Mining Institute Kola Science Centre of the Russian Academy of Sciences, Apatity, Russian Federation
References
1. Захаров В.Н., Гвишиани А.Д., Вайсберг Л.А., Дзеранов Б.В. Большие данные и устойчивое функционирование горнотехнических систем. Горный журнал. 2021;(11):45–52. https://doi.org/10.17580/gzh.2021.11.06 Zakharov V.N., Gvishiani A.D., Vaisberg L.A., Dzeranov B.V. Big Data and sustainable functioning of geotechnical systems. Gornyi Zhurnal. 2021;(11):45–52. (In Russ.) https://doi.org/10.17580/gzh.2021.11.06
2. Рыльникова М.В., Алексеев А.Б., Есина Е.Н., Зотеев О.В., Ливинский И.С., Макаров А.Б. и др. Методические указания по оценке рисков развития деформаций, мониторингу и управлению устойчивостью бортов и уступов, карьеров, разрезов и откосов отвалов. М.: ИПКОН РАН; 2022. 90 с.
3. Rozanov I.Yu., Zavyalov A.A. Specifics in organization of the slope stability monitoring in high-strength hard rock massif of the Kovdor deposit. In: Litvinenko V. (ed.) Topical Issues of Rational Use of Natural Resources 2019. Vol. 1: Proceedings of the XV International Forum-Contest of Students and Young Researchers under the auspices of UNESCO (St. Petersburg Mining University, Russia, 13–17 May 2019). London: CRC Press; 2019, pp. 229–234. https://doi.org/10.1201/9781003014577-29
4. Рыбин В.В., Константинов К.Н. Каган М.М. Панасенко И.Г. Принципы организации комплексной системы мониторинга устойчивости объектов горнодобывающего предприятия. Горный журнал. 2020;(1):53–57. https://doi.org/10.17580/gzh.2020.01.10 Rybin V.V., Konstantinov K.N., Kagan M.M., Panasenko I.G. Methodology of integrated stability monitoring in mines. Gornyi Zhurnal. 2020;(1):53–57. (In Russ.) https://doi.org/10.17580/gzh.2020.01.10
5. Рыбин В.В., Константинов К.Н., Наговицын О.В. Структура комплексной системы мониторинга устойчивости объектов открытых горных работ с применением цифровых технологий. Физико-технические проблемы разработки месторождений полезных ископаемых. 2021;(4):70–77. https://doi.org/10.15372/FTPRPI20210407 Rybin V.V., Konstantinov K.N., Nagovitsyn O.V. Structure of integrated stability monitoring in open pit mining using digital technologies. Journal of Mining Science. 2021;57(4):601–606. https://doi.org/10.1134/S1062739121040074
6. Рыбин В.В., Константинов К.Н., Розанов И.Ю. Многоуровневый подход к организации мониторинга устойчивости бортов карьеров. Физико-технические проблемы разработки месторождений полезных ископаемых. 2021;(5):106– 113. https://doi.org/10.15372/FTPRPI20210510 Rybin V.V., Konstantinov K.N., Rozanov I.Y. A multilevel approach to pitwall stability monitoring. Journal of Mining Science. 2021;57(5):805–811. https://doi.org/10.1134/S1062739121050100
7. Захаров В.Н., Каплунов Д.Р., Клебанов Д.А., Радченко Д.Н. Методические подходы к стандартизации сбора, хранения и анализа данных при управлении горнотехническими системами. Горный журнал. 2022;(12):55–61. https://doi.org/10.17580/gzh.2022.12.10 Zakharov V.N., Kaplunov D.R., Klebanov D.A., Radchenko D.N. Methodical approaches to standardization of data acquisition, storage and analysis in management of geotechnical systems. Gornyi Zhurnal. 2022;(12):55–61. (In Russ.) https://doi.org/10.17580/gzh.2022.12.10
8. Каган М.М., Чернобров Д.С. Мониторинг сейсмоактивности прибортового массива карьера на основе сейсморегистраторов в глубоких скважинах за конечным контуром. Горная промышленность. 2023;(S1):84–88. https://doi.org/10.30686/1609-9192-2023-S1-84-88 Kagan M.M., Chernobrov D.S. Monitoring of seismic activity in near-wall rock masses of open pits using seismic recorders in deep boreholes beyond the final pit boundary. Russian Mining Industry. 2023;(1 Suppl.):84–88. (In Russ.) https://doi.org/10.30686/1609-9192-2023-S1-84-88
9. Рыбин В.В., Константинов К.Н., Старцев Ю.А. Оценка динамики изменения упругих характеристик массива пород в борту карьера. Физико-технические проблемы разработки полезных ископаемых. 2023;(5):40–46. Rybin V.V., Konstantinov K.N., Startsev Yu.A. Time history of elastic characteristics in pitwall rock mass. Fiziko-Tekhnicheskie Problemy Razrabotki Poleznykh Iskopaemykh. 2023;(5):40–46. (In Russ.)
10. Захаров В.Н., Клебанов Д.А., Макеев М.А., Радченко Д.Н. Анализ методов подготовки и преобразования информации, поступающей в хранилища данных для эффективного управления горнотехнической системой. Горная промышленность. 2023;(5S):10–17. https://doi.org/10.30686/1609-9192-2023-5S-10-17 Zakharov V.N., Klebanov D.A., Makeev M.A., Radchenko D.N. Analysis of methods to prepare and transform information entering data repositories for effective management of the mining system. Russian Mining Industry. 2023;(5S):10–17. (In Russ.) https://doi.org/10.30686/1609-9192-2023-5S-10-17